Virginia’s Loudoun County defers decisions on data centre applications for up to a year

AI-generated contentWritten by AI

loudoun.gov, datacenterdynamics.com, commercialobserver.com, fox5dc.com · 5 sources · Sources published: 17–18 November 2026 · Some source publication dates are unknown

Loudoun County, the world’s largest data centre cluster, is deferring decisions on data centre and substation applications for up to 12 months, which could affect 33 pending applications. It is not a construction ban: developers can still submit applications, and some projects are going ahead.

Loudoun County’s Board of Supervisors made the decision on 17 November, the county said in a press release. The pause applies retroactively from 15 September and ends when the board approves amendments to the comprehensive plan and zoning ordinance covering where data centres can be located and how they must be built. The vote was 7–1 with one abstention, trade publication DCD and Commercial Observer reported.

DCD calls the decision a moratorium, but a legal opinion from the County Attorney found that a moratorium stopping all approvals would be illegal. The board is therefore deferring only its own decisions. Virginia law requires a decision within a year of an application reaching the Planning Commission, so no single application can be deferred for longer than that. Developers can still submit applications, and county staff prepare them for Planning Commission hearings.

The pause covers only applications the board votes on. It excludes applications decided administratively and properties in the Route 28 Tax District. The board may also consider exceptions for applications that support electric grid reliability and where the statutory deadline is about to expire. Citing other media, Commercial Observer reported that 15–17 projects or administrative applications covered by the old zoning rules may proceed despite the pause.

DCD, drawing on meeting documents, counted 33 pending applications: ten data centres, ten combined data centre and substation applications, one substation supporting grid reliability and 12 other substations that do not support reliability or are part of combined projects.

Local outlet FOX 5 DC reported a 10-month pause without explaining the figure, whereas the county speaks of up to 12 months. Sources also differ on when the pause ends: DCD says September 2027, while the county ties it to approval of the zoning amendments, expected in summer 2027.

County staff estimate that clearing the backlog could require 4–6 months of additional meetings from autumn 2027, Commercial Observer reported. Staff also noted that the decision could lead to lawsuits from developers, DCD reported. The industry group Data Center Coalition warned that the abrupt change of direction adds uncertainty and disrupts investment.

A county fact sheet cited by DCD lists 245 data centres in operation or under construction. The 2027 budget projects $1.3 billion in data centre revenue, or 40 per cent of the budget.